right side of road 0-115' add road bond 3' wide 4" deep 115' long= 4.26 cubic yards
at 115' pavement is under cut and cracking, add road bond
303'-383' remove surge stone add crusher run 3' wide 4" deep 80' long= 2.96 cubic yards
383'-645' add road bond 3'wide 4" deep 262' length= 9.7 cubic yards
498'-645"' remove rip rap, add road bond 3' wide, 4" deep,147' length= 5.4 cubic yards
645'-674', erosion and washing, add road bond, 3' wide, 4" deep, 29' long = 1.07 cubic yard
940' to Gray Cottage Lane, pave ditch is in good shape.
left side of road, heading toward the lodge. =0
0 -53' add crusher run 3' wide 4" deep 53' long 1.96 cubic yard
93'-1089 (stop sign add crusher run 3' wide 4" deep, 40' long 996= 36.89 cu yard
cubic yards of crusher run 63.66
remove and relocate large stone
grass seed... and mat for 10,000 sq feet
4 men 5 days
1 truck, ton dump
one Bob Cat track loader 5 days